At last, the 116-year-old N.J. bridge that made commuting hellish has been replaced
Key Points:
- The $2.3 billion Portal North Bridge, carrying the nation's busiest passenger rail line over the Hackensack River, officially opened after a five-week cutover project, eliminating delays caused by the old 116-year-old swing bridge.
- The new fixed-span bridge stands 50 feet above the river, allowing uninterrupted train service without opening for boats, and supports speeds up to 90 mph, significantly improving efficiency on the Northeast Corridor.
- Officials, including NJ Transit CEO Kris Kolluri and New Jersey Gov. Mikie Sherrill, praised the project for ending chronic delays, enhancing commuter experiences, and contributing to regional economic productivity.
- The project was completed on time and slightly under budget, with ongoing work including demolition of the old bridge and construction of a new viaduct, which will not disrupt service.
- Federal funding totaling $926 million was crucial for the project, with significant support from New Jersey’s congressional delegation, who were recognized for their efforts in securing the necessary resources.