SpaceXAI Says It Will Take A Year To Fully Remove Unpermitted Gas Turbines From Its Mississippi Data Center
AI Generated Image

SpaceXAI Says It Will Take A Year To Fully Remove Unpermitted Gas Turbines From Its Mississippi Data Center

Engadget business

Key Points:

  • SpaceX plans to fully remove its unpermitted gas turbines powering the SpaceXAI data center near Memphis, Tennessee by July 2027, following a company update reported by TechCrunch.
  • The turbines are currently involved in a NAACP lawsuit alleging that they expose nearby communities to harmful chemicals and pollution, violating the Clean Air Act.
  • SpaceX is constructing a new 1.2GW power plant in Mississippi under a Clean Air Act permit to replace the 69 unpermitted turbines, with removal set to begin in August 2026 and conclude by July 2027.
  • SpaceX acquired xAI in February 2026 and faces legal challenges from the NAACP, which sued xAI over its unpermitted turbines and the associated health risks such as asthma and cancer.
  • Despite the lawsuit, SpaceXAI asserts that current data indicates local air quality meets or exceeds EPA standards.